To read a tender notice, you don’t need to read every field. A notice can look like a wall of them. You need a scan order that tells you, in about five minutes, whether to open the tender pack at all.
This guide gives you that order for a notice under the Procurement Act 2023, and shows you where the real requirements tend to be. It is part of our SME guide to winning public contracts.
Tender notice vs tender documents
The notice and the documents are not the same thing.
Both procedures under the Act begin with the publication of a tender notice (para 1). It goes on the Central Digital Platform and gives access to any associated tender documents, which add detail such as the specification and contract terms. Where those documents are used, they must generally be provided free of charge and electronically (para 19).
In the open procedure, the notice is the invitation to tender, and the associated documents are published at the start so you can begin straight away (para 34). In the competitive flexible procedure, the notice can instead invite requests to participate first (para 47).
So the notice is the front page. It tells you what is being bought, by whom, and when it closes. The detail lives in the documents.
The five-minute scan: 8 things to check, in this order
The order matters. It puts the things that can rule you out first.
1. Closing date and time
Find the deadline and put it in your diary. The notice must say how and by when to submit (para 85).
Then work backwards. Under the open procedure the minimum tendering period is 25 days where tenders are submitted electronically and all the tender documents come with the notice. It is 30 days if only one of those is true, and 35 if neither (para 20(g)–(j)). It can be 10 days in some cases, for example after a qualifying planned procurement notice (para 20). There is no minimum for light touch contracts (para 20(a)). Those are minimums, and the notice may give you longer.
Below threshold, the rule is different: time limits must be reasonable and the same for all suppliers (s.87(6)).
Look for an earlier deadline too. Buyers ask for core supplier information through the platform at a point they set, which should be before the tendering period ends (para 66).
2. Procedure: open or competitive flexible
Is it an open procedure, where you tender now, or a competitive flexible one, where a request to participate may come first?
In the competitive flexible procedure, a request to participate is a supplier’s response expressing interest (para 56), and the buyer may use it to limit how many suppliers go on to tender. That changes your workload. You may write a short submission first, and a full tender only if you’re invited.
3. Value and contract length
Check whether a value is stated and whether it includes VAT. The Act’s thresholds are stated including VAT, but stated values in notices may or may not be. Don’t compare them with a threshold without checking.
Note the contract length and any extensions. A £90,000 contract over three years is £30,000 a year, which matters for cash flow and for any turnover test.
4. Lots, and any limit on how many you can bid for
Does the work split into lots? A buyer can limit the number of lots one supplier can tender for, and must state that maximum in the tender notice (para 14). It must also state any cap on lots a supplier can be awarded, and how it will choose (s.23(4)).
As of 10 Oct 2026, 62 of 470 live notices were multi-lot. If yours is, find the lot that matches your size and location, and read its requirements separately.
5. Where the work is delivered
Check the delivery location and, if you can find it, the frequency of visits. A cleaning contract spread over five towns is a different proposition from one site.
Be careful with region tags. As of 10 Oct 2026, about a third of live notices were tagged only “UK” or had no region, so the real location may only appear in the documents.
6. Conditions of participation
This is the pass/fail section: insurance, certifications, turnover, experience. The notice should include a description of the conditions of participation (para 85). A supplier must meet all of them to be awarded the contract (para 24). Read it carefully, and see below for what the law lets a buyer ask.
7. Award criteria and weightings
The notice must include the award criteria or a summary of them (para 85). These are what your response is scored against. Note the split between price and quality, and any criterion that is pass/fail.
8. How and where to submit
Find out whether you submit through the buyer’s portal, whether an electronic auction is used, and what the payment terms are. The notice must state any payment terms beyond the implied 30 days (s.68; para 85). If you need an account on the buyer’s portal, set it up now, not on the closing day.
What to write down after the scan
Don’t rely on memory. After the five minutes, jot down one line for each of these:
- the buyer, the title and the link to the official notice
- the closing date and time, and the date you want a draft finished
- the procedure (open, or competitive flexible with a request to participate)
- the lot you’re looking at, and any limit on lots
- what the notice says about insurance, certifications and turnover, and what it leaves out
- the weightings, and any pass/fail criterion
That page becomes the first entry in your bid log. If you decide to go on, it also tells you what to hunt for in the pack.
What the notice can’t tell you
A notice is a summary. It can’t tell you how the buyer will treat a borderline case, how many others will bid, or whether the incumbent is already doing the job. The notice may not include the exact insurance levels, the staff vetting requirements or the contract’s full terms either. Treat any gap as a question for the pack, or for a clarification question to the buyer, rather than as a “no”.
Where requirements hide
Here is the honest bit. Notices tell you where to look more often than they tell you what is required.
In the week to 10 Oct 2026, 29 of 470 live notices (about 6%) stated insurance requirements in the notice itself, and 29 stated named certifications (as of 10 Oct 2026; how we count). For the rest, any requirements will be in the tender pack.
When you open the pack, look in these places:
- the invitation to tender or instructions to bidders
- the participation or suitability questions
- the contract terms and conditions
- the specification, for accreditation and staffing requirements
Write down every requirement you find, with the page number. That list is the input to your bid or no-bid decision.
Reading conditions of participation properly
Conditions of participation must be a proportionate means of ensuring you have the legal and financial capacity, or the technical ability, to perform the contract (s.22(1)), judged against its nature, complexity and cost (s.22(5)). The Act sets limits that you can use:
- Insurance. On above-threshold contracts, a buyer can’t require insurance relating to performance of the contract to be in place before award (s.22(3)(b)), except insurance you must hold by law anyway, such as employers’ liability, which can be a condition of participation (para 20). For other cover it can require it from contract start and ask for a certificate, or an insurer’s letter plus your commitment, verified before award (paras 18 and 19). Below threshold, s.85 bars a suitability stage. See public liability insurance for tenders, which also covers employers’ liability.
- Accounts. A buyer can’t require audited accounts unless you are already required to have them audited (s.22(3)(a); paras 16 and 17). See turnover and financial standing tests.
- Qualifications. A named qualification must allow equivalents (s.22(4)(c)). See ISO 9001 and Cyber Essentials.
- Partners. You count as meeting a condition to the extent an associated supplier does (s.22(8) and (9)).
None of these makes a gap automatically fixable. They just mean a gap isn’t automatically fatal.
Our tender eligibility checker is coming soon. Until then, tell us your trade and postcode to join the free weekly list of live tenders, starting soon.
Reading the award criteria
The buyer must set out how tenders will be assessed and the relative importance of the criteria, for example as percentages (s.23(3)). If failing a criterion would disqualify a tender, the methodology must say so (para 13).
Read the weightings before the questions. If price is 40% and quality 60%, and one quality question is worth 20 points on its own, you know where your time goes. See how tenders are scored.
Worked example: a notice, annotated
This example is invented for illustration. It is not a real tender.
Imagine a council notice for grounds maintenance services, in three lots by area, with a stated value of £300,000 over three years. That is above the £207,720 threshold for services bought by councils, so the full Act rules apply.
| Field in the notice | What it says | What to think |
|---|---|---|
| Procedure | Open | You can tender now. No request to participate |
| Closing | 26 days away | Fits the 25-day minimum for an open procedure with electronic submission and documents published with the notice. Check your diary now |
| Value | £300,000, VAT not stated | About £100,000 a year. Check VAT in the pack |
| Lots | 3, bid for a maximum of 2 | Pick the two that suit your depots |
| Conditions | “Appropriate insurance and relevant accreditation” | Vague. Open the pack and find the figures |
| Award | 60% quality, 40% price, one pass/fail health and safety question | Don’t skimp on health and safety evidence |
In that example you’d learn most of what matters in five minutes, except the actual insurance levels. That is what the pack is for.
Red flags that mean “probably not for us”
These are our rules of thumb, not legal tests. Stop, or at least pause, if you see:
- delivery far outside the area you can serve
- a lot structure where no single lot fits your size
- conditions you can’t meet by contract start, such as a certification that takes months you don’t have
- a closing date that leaves less time than the response needs
- a pass/fail criterion you can’t evidence
A single red flag isn’t always the end. You might fix it with a partner. But two or three together usually are.
Next step: bid or no bid
You’ve scanned the notice and, if it still looks right, opened the pack. Now decide properly with our bid or no-bid checklist.
If you’d rather have the scanning done for you, tell us your trade and postcode to join the free weekly list of live tenders, starting soon. On Pro (£49/month), notices that fit your trade and area are checked against what each states about insurance, certifications and location, and you get an email each morning on days with new matches.
Questions
What's the difference between a tender notice and tender documents?
The tender notice starts the procedure and is published on the Central Digital Platform. Associated tender documents add detail, such as the specification and contract terms. They must generally be provided free of charge and electronically, and in the open procedure they are published at the outset alongside the notice.
Where do I find the insurance and certification requirements?
Often in the tender documents rather than the notice. In the week to 10 Oct 2026, about 6% of live notices (29 of 470) stated insurance requirements in the notice itself (as of 10 Oct 2026). Where they are not in the notice, look in the invitation to tender, the participation questions and the contract terms.
What does 'request to participate' mean?
It is a supplier's response to a tender notice expressing interest, used in the competitive flexible procedure when a buyer wants to limit how many suppliers are invited to tender. In the open procedure there is no such stage: any interested supplier can tender straight away.
What if I don't have the insurance level they ask for yet?
On above-threshold contracts, a buyer cannot require insurance relating to performance of the contract to be in place before award (section 22(3)(b)), except insurance you must hold by law anyway, such as employers' liability, which can be a condition of participation (conditions of participation guidance, para 20). For other cover it can require the cover from the start of the contract and ask for evidence, such as an insurer's letter, which it verifies before award. Below threshold, [s.85](https://www.legislation.gov.uk/ukpga/2023/54/section/85) bars a separate suitability stage before tenders are submitted, but the buyer can still assess suitability, including insurance, at the award stage (below-threshold guidance para 16; exceptions in paras 18 and 20). Check exactly what the pack asks for and when.
Are tender documents free?
Generally yes. The guidance says associated tender documents must generally be provided free of charge and electronically. If a buyer asks you to pay for the documents, question it before you do.